The objective of this remedial action was to locate, remove, and dispose of abandoned transformers at the Federal Aviation Administration (FAA) Biorka Island site and remove associated impacted soil.

The remedial action included: removal and containerization of two transformers; excavation of impacted soil located beneath the transformers; collection of soil samples at excavation limits for analysis of diesel range organics (DRO); residual range organics (RRO); polycyclic aromatic hydrocarbons (PAHs); and polychlorinated biphenyls (PCBs); characterization of the soil located inside of the transformers and soil removed from the excavation; and transport and disposal of the transformers and excavated soil.

CLIENT

Federal Aviation Administration

CONTRACT NO.

DTFASA-17-P-00701

PROJECT VALUE

$26,364

YEAR COMPLETED

2017

NAICS

562910